X

Squaw Creek Water Supply Level II Study

Teton County, Wyoming

Cost:     $521K Construction Cost Estimate @ 1.5 M (Pending)

Phase I $172k Construction Cost: Estimate @$1.5M (Pending Completion of Level II and Level III appropriation)

Phase II & III $348.4K

Professional Service Date:  June 2010 – December 2015 Completion Date 2011

SERVICES PROVIDED:  Construction Management Surveying, Planning, Permitting, Consents, Landowner Negotiations, Supervision of Well Drilling and Pump Testing

Client: Wyoming Water Development Commission, Cheyenne, WY 

The Wyoming Legislature as part of the new development program authorized this project for the Wyoming Water Development Commission.http://wwdc.state.wy.us/

AVI and Dahlgren Consulting were selected to perform a Level II study to identify a supplemental water source for the Squaw Creek Water District in Teton County.  The District has 75 homes on its water system.  The current water supply consists of two alluvial wells on Game Creek and a developed spring source.  These sources are potentially subject to influence of surface water and are barely adequate to meet District demands despite an aggressive schedule of water rates.

The contract for the first phase of the work was signed on June 11, 2010 and directed AVI to complete a Level II study of the District’s water system including an evaluation of supply, transmission, distribution, water rights, operations, water quality, and population/demand, identification of alternatives, cost estimates, and recommendations.  This phase included a pump test of an existing well and evaluation of multiple supply options but did not identify a viable source of new supply.

The contract amended in March of 2013, to provide funds for the construction of a test well on the Bridger Teton National Forest.  The well did not produce sufficient water to justify cost of a pipeline to the District. The test well required the acquisition of Special Use Permits from the US Forest Service and the Wyoming Game and Fish Department.

In 2014, AVI initiated negotiations with a private landowner and with the WGFD for additional test well sites.  If a successful well is developed, AVI will design a water line and appurtenances necessary to connect to the District’s existing system.  With concurrence from the District and WWDO, an application for Level III funding will be prepared.

They were particularly good working with the contractors. The skillset of the group was particularly strong with civil engineering and road/drainage designs, but not quite as strong in natural channel design principles. – Luke Schultz – Coal Creek Sediment Reduction and Bank Stabilization

 

 

Luke Schultz – Coal Creek Sediment Reduction and Bank Stabilization

AVI personnel working on this project have provided excellent service and good responsiveness. Very much team players and valuable as resources.

Marcia Murdock, AML Project Manager

AVI completed a very good report, detailing multiple surfacing options and developed cost estimates for each option — good job!

Kevin Stogsdill, PE-WYDOT Interstate 80 RECON

I was very impressed by the timely efforts including straightening out the problem R/W survey that had stalled the project for years.

Dan Lyons, PE-WYDOT Veteran Road

AVI is one of our best consultants. They have proven they can handle multiple projects at one time. WYDOT would be hard pressed to give AVI a project they could not handle.

Cliff Spoonemore, PE-WYDOT Snowy Range Road