Loveland Housing Projects

2017 Roadway Projects

Kings Canyon:

Construction Status: Land owner (Loren Carlson) has asked for added work to be completed to remove a rock near approach that could be affecting culvert hydraulically. Jon Beckett has equipment in the area and told land owner he would perform the work and would take 15 minutes.

Estimated Completion: Summer 2017

Construction Cost: No added cost

 Loveland Heights:

Construction Status: All grading and pipe installation efforts are complete at this time. Contractor put off paving until Summer 2017. A bid to perform the paving has been requested for and has yet to be submitted by the contractor.

Estimated Completion: Summer 2017

Construction Cost: $37,921.50 w/o paving

 Boogie Woogie Way:

Construction Status: Work substantially complete. Additional work requested by land owner to address fore slopes along existing drainage ditch just north of CR 44H.

Estimated Completion: Summer 2017

Construction Cost – Unknown

 Spencer Mountain Road:

Construction Status: Construction work commenced week of 6/19

Estimated Completion: Middle July 2017

Construction Bid Cost – $228,488.00 (Project is expected to over-run with added 2,000’ of roadway onto the end of the project, requested added cost from contractor)

Paradise Park Road:

Construction Status: Contract awarded to Custom Design Fabricators (Pre-construction Meeting held 5/31)

Estimated Completion: Beginning August 2017

Construction Bid Cost: $141,734.50 (Project is expected to over-run with added culvert removal and replacement, requested added cost from contractor)

 Rist Creek Road:

Construction Status: Construction underway with project currently approximately 50% complete

Estimates Completion: End of June 2017

Construction Bid Cost – $187,380.50

 Patience Way:

Construction Status: Contract awarded to Road Runner Grading

Estimated Completion: End of July 2017

Construction Bid Cost: $45,400.00

 256 George Stadler Road (Dykstra):

Construction Status: Contract awarded to Custom Design Fabricators (Pre-construction Meeting held 5/31)

Estimated Completion: Beginning of July 2017

Construction Bid Cost: $31,989.25

 2017 Crossing Projects

 Cedar Brook:  

Construction Status: Contract awarded to Road Runner Grading

Estimated Completion: End of August 2017

Construction Bid Cost: $171,131.00

 Glen Haven:

Construction Status: Construction approximately 75% complete

Estimated Completion: End of June 2017

Construction Bid Cost: $317,711.00

 Pine Valley:

Construction Status: Project Awarded to Coal Creek Excavation (Pre-Construction Meeting held 5/22)

Estimated Completion: End of July 2017

Construction Bid Cost: $178,480.00

 9469 Rist Canyon (Levick):

Construction Status: Project currently under construction with installation of culvert to commence week of 6/19

Estimated Completion: Middle of July 2017

Construction Bid Cost: $79,380.00

 10548 CR 43 (Mccallum):

Design Status: Working through final design and bid documents

Estimated Completion: Fall 2017

Estimated Construction Cost: $414,000.00

 10518 CR 43 (Pat Karspeck):

Design Status: Working through final design, bid documents, and access and construction easement documents

Estimated Completion: Fall 2017

Estimated Construction Cost: $375,000.00

 12444 CR 43 (Mary Allen):

Design Status: Working through final design bid documents, and access and construction easement documents

Estimated Completion: Fall 2017

Estimated Construction Cost – $365,000.00

 13500 CR 25E (Friede):

Design Status – Working through preliminary design and hydraulic evaluations

Estimated Completion: Fall 2017

Estimated Construction Cost – $200,000.00

 

 

They were particularly good working with the contractors. The skillset of the group was particularly strong with civil engineering and road/drainage designs, but not quite as strong in natural channel design principles. – Luke Schultz – Coal Creek Sediment Reduction and Bank Stabilization

 

 

Luke Schultz – Coal Creek Sediment Reduction and Bank Stabilization

AVI personnel working on this project have provided excellent service and good responsiveness. Very much team players and valuable as resources.

Marcia Murdock, AML Project Manager

AVI completed a very good report, detailing multiple surfacing options and developed cost estimates for each option — good job!

Kevin Stogsdill, PE-WYDOT Interstate 80 RECON

I was very impressed by the timely efforts including straightening out the problem R/W survey that had stalled the project for years.

Dan Lyons, PE-WYDOT Veteran Road

AVI is one of our best consultants. They have proven they can handle multiple projects at one time. WYDOT would be hard pressed to give AVI a project they could not handle.

Cliff Spoonemore, PE-WYDOT Snowy Range Road